Belvedere · Hedutane, Thane · Lodha Developers Limited
Promised for 29 Feb 2028, extended to 29 Jun 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 29 Feb 2028 to 29 Jun 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51700052237
Is Belvedere delayed?
Its completion moved from 29 Feb 2028 to 29 Jun 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51700052237. The completion date moved from 29 Feb 2028 to 29 Jun 2028.
Who is the promoter?
MahaRERA records Lodha Developers Limited as the promoter of P51700052237.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700052237.