Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P51700050529

Ramdarshan Residency · Titwala, Thane · Shree Sai Gajanan Developers

Promised for 1 Feb 2027, extended to 1 Jun 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Feb 2027 to 1 Jun 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700050529

Is Ramdarshan Residency delayed?

Its completion moved from 1 Feb 2027 to 1 Jun 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700050529. The completion date moved from 1 Feb 2027 to 1 Jun 2027.

Who is the promoter?

MahaRERA records Shree Sai Gajanan Developers as the promoter of P51700050529.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700050529.

Answers are generated from the record.

Data through4 Nov 2026, 02:00SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology