RegisteredExtendedMahaRERA status: Certificate Signed

P51700048753

Sumeet Elite · Balkum, Thane · Vedant Construction

Promised for 31 May 2027, extended to 30 Sep 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 May 2027 to 30 Sep 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate11 Sep 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700048753

Is Sumeet Elite delayed?

Its completion moved from 31 May 2027 to 30 Sep 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700048753. The completion date moved from 31 May 2027 to 30 Sep 2027.

Who is the promoter?

MahaRERA records Vedant Construction as the promoter of P51700048753.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700048753.

Answers are generated from the record.

Data through4 Nov 2026, 02:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology