Registered1 extensionMahaRERA status: Certificate Signed

P51700047773

Raghunath Heights · Kalher (Ct), Thane · Khrushna Infrastructure Builders & Developers

Promised for 31 Dec 2025, extended once to 31 Dec 2028, which is still ahead.

The revised date is 3 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2025 to 31 Dec 2028 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate28 Nov 2022View
Extension certificate17 Feb 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700047773

Is Raghunath Heights delayed?

Its completion moved from 31 Dec 2025 to 31 Dec 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700047773. The completion date moved from 31 Dec 2025 to 31 Dec 2028.

Who is the promoter?

MahaRERA records Khrushna Infrastructure Builders & Developers as the promoter of P51700047773.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700047773.

Answers are generated from the record.

Data through4 Nov 2026, 02:04SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology