Registered1 extensionMahaRERA status: Certificate Signed

P51700046454

Shambhu Shankar Residency · Sonale, Thane · Vidisha Constructions

Promised for 20 Dec 2026, extended once to 20 Apr 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 20 Dec 2026 to 20 Apr 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate14 Aug 2026View
Registration certificate21 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700046454

Is Shambhu Shankar Residency delayed?

Its completion moved from 20 Dec 2026 to 20 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700046454. The completion date moved from 20 Dec 2026 to 20 Apr 2027.

Who is the promoter?

MahaRERA records Vidisha Constructions as the promoter of P51700046454.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700046454.

Answers are generated from the record.

Data through30 Oct 2026, 02:44SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology