Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passedExtendedMahaRERA status: Certificate Signed

P51700045235

Seva Smruti · Dombivli, Thane · Neelpadma Associates

Promised for 31 May 2026, extended to 30 Sep 2026 — and that date has passed without the project marked complete on MahaRERA.

5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 May 2026 to 30 Sep 2026.
  • Risk: The latest completion date on record, 30 Sep 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate13 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700045235

Is Seva Smruti delayed?

Yes. MahaRERA records a promised completion of 31 May 2026, revised to 30 Sep 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700045235. The completion date moved from 31 May 2026 to 30 Sep 2026.

Who is the promoter?

MahaRERA records Neelpadma Associates as the promoter of P51700045235.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700045235.

Answers are generated from the record.

Data through25 Oct 2026, 02:59SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology