Neelpadma Associates

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rangrekha HeightsP51700021033Dombivli2019Not reported30 Dec 2022—On date
Pranjali HeightsP51700023874Dombivli2020Not reported30 May 202231 Dec 2022+7 months
Audumbar CHSP51700034542Dombivli2022Not reported31 Dec 2023—On date
Seva SmrutiP51700045235Dombivli2022Not reported31 May 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rangrekha HeightsOn date
  • Pranjali Heights+7 mo
  • Audumbar CHSOn date
  • Seva SmrutiOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 7 months, for Pranjali Heights (P51700023874).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology