Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700033810

Ayesha Garden · Kalyan, Thane · Azka Builders And Developers

Promised for 31 Dec 2024, extended once to 30 Sep 2025 — and that date has passed without the project marked complete on MahaRERA.

1 year and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2024 to 30 Sep 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 Feb 2025View
Extension certificate24 Mar 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700033810

Is Ayesha Garden delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2024, revised to 30 Sep 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700033810. The completion date moved from 31 Dec 2024 to 30 Sep 2025.

Who is the promoter?

MahaRERA records Azka Builders And Developers as the promoter of P51700033810.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700033810.

Answers are generated from the record.

Data through3 Nov 2026, 02:10SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology