RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700012148

Usha Joshi Park Phase B · Khadavali, Thane · J K T Builders & Developers

Promised for 30 Dec 2021, extended once to 30 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2021 to 30 Jun 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate9 Sep 2021View
Extension certificate2 Feb 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700012148

Is Usha Joshi Park Phase B delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, revised to 30 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700012148. The completion date moved from 30 Dec 2021 to 30 Jun 2023.

Who is the promoter?

MahaRERA records J K T Builders & Developers as the promoter of P51700012148.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700012148.

Answers are generated from the record.

Data through23 Nov 2026, 01:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology