Completed

P51700010195

Laabh Neelkanth · Thane (M Corp.), Thane · Laabh Buildtech

Promised for 31 Dec 2019; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 19

Title report29 Jul 2017View
Encumbrance details29 Jul 2017View
Commencement certificate29 Jul 2017View
Form 129 Jul 2017View
Form B30 Jul 2017View
Form 230 Jul 2017View
Registration certificate24 Aug 2017View
Form 223 Apr 2018View
Show all 19 documents
Form 514 Oct 2018View
Occupancy / completion certificate20 Oct 2019View
Form 43 Jan 2020View
Form 54 Feb 2020View
OtherView
OtherView
Layout planView
Building planView
Allotment letterView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700010195

Is Laabh Neelkanth delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2019.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700010195.

Who is the promoter?

MahaRERA records Laabh Buildtech as the promoter of P51700010195.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700010195.

Answers are generated from the record.