Completed
P51700010108
Indira Niwas Annex · Thane (M Corp.), Thane · Shree Swami Krupa Builders And Developers
Promised for 31 Dec 2018; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 21
Orders 0
No MahaRERA order or list names this number.
Questions about P51700010108
Is Indira Niwas Annex delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2018.
How many extensions has it had?
Deedo holds 0 extension certificates for P51700010108.
Who is the promoter?
MahaRERA records Shree Swami Krupa Builders And Developers as the promoter of P51700010108.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700010108.