Completed

P51700009847

Aditya Royal · Ambarnath(M Cl), Thane · Prashant Aditya Shukla

Promised for 30 Jun 2018; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: 3 other MahaRERA orders name this registration.
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 31

Title report30 Jul 2017View
Title report30 Jul 2017View
Encumbrance details30 Jul 2017View
Form B30 Jul 2017View
Form 130 Jul 2017View
Form 230 Jul 2017View
Allotment letter30 Jul 2017View
Allotment letter30 Jul 2017View
Show all 31 documents
Registration certificate22 Aug 2017View
Form 49 Jan 2020View
OtherView
Layout planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 3

Suo motu order

Suo motu order: Secretary, MahaRERA Versus Prashant Aditya Shukla (Suo Motu Case No. 43 of 2020) dated 10th February 2020

11 Feb 2020 · matched by RERA number

View order →

Questions about P51700009847

Is Aditya Royal delayed?

MahaRERA reports it completed. Its promised completion date was 30 Jun 2018.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700009847.

Who is the promoter?

MahaRERA records Prashant Aditya Shukla as the promoter of P51700009847.

Is it on any MahaRERA regulatory list?

3 MahaRERA orders or lists name P51700009847.

Answers are generated from the record.

Data through23 Nov 2026, 01:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology