Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P51700006338

Building G Sai Icon Phase 2 · Kalyan, Thane · Mutha Properties

Promised for 30 Dec 2023, extended once to 31 Dec 2028, which is still ahead.

The revised date is 5 years after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2023 to 31 Dec 2028 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate22 Nov 2023View
Extension certificate19 Jan 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700006338

Is Building G Sai Icon Phase 2 delayed?

Its completion moved from 30 Dec 2023 to 31 Dec 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700006338. The completion date moved from 30 Dec 2023 to 31 Dec 2028.

Who is the promoter?

MahaRERA records Mutha Properties as the promoter of P51700006338.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700006338.

Answers are generated from the record.

Data through9 Nov 2026, 01:52SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology