Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51600023066

Sai Ganesh Residency · Nashik · Hitesh Masnhukhbhai Virpara Huf

Promised for 30 Sep 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 2 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Sep 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51600023066

Is Sai Ganesh Residency delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600023066.

Who is the promoter?

MahaRERA records Hitesh Masnhukhbhai Virpara Huf as the promoter of P51600023066.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600023066.

Answers are generated from the record.

Data through4 Nov 2026, 02:44SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology