Completed

P51600018928

Panchami Residency · Nashik (M Corp.), Nashik · S K Buildcon

Promised for 30 Dec 2022; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

    Documents 26

    Title report13 Dec 2018View
    Encumbrance details13 Dec 2018View
    Commencement certificate13 Dec 2018View
    Form B13 Dec 2018View
    Form 2A12 Jan 2019View
    Form 2A20 Jul 2019View
    Form 18 Feb 2020View
    Form 28 Feb 2020View
    Show all 26 documents
    Occupancy / completion certificate5 May 2020View
    Form 46 May 2020View
    Other6 May 2020View
    Other6 May 2020View
    Other6 May 2020View
    Other6 May 2020View
    Form 110 Sep 2020View
    Form 210 Sep 2020View
    Form 510 Sep 2020View
    Registration certificate9 Sep 2021View
    OtherView
    OtherView
    Layout planView
    Building planView
    OtherView
    OtherView
    OtherView
    Allotment letterView

    Orders 0

    No MahaRERA order or list names this number.

    Questions about P51600018928

    Is Panchami Residency delayed?

    MahaRERA reports it completed. Its promised completion date was 30 Dec 2022.

    How many extensions has it had?

    Deedo holds 0 extension certificates for P51600018928.

    Who is the promoter?

    MahaRERA records S K Buildcon as the promoter of P51600018928.

    Is it on any MahaRERA regulatory list?

    No MahaRERA order or list that Deedo holds names P51600018928.

    Answers are generated from the record.