Completed

P51600017075

Shrinathji Palace Co-Opp Housing Society Ltd. · Nashik · Shrinathji Palace CoOpp Hsg Society Ltd

Promised for 30 Jun 2023; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Title report23 Jun 2018View
Commencement certificate23 Jun 2018View
Form 123 Jun 2018View
Encumbrance details5 Jul 2018View
Form B5 Jul 2018View
Form 25 Jul 2018View
Form 530 Sep 2019View
Occupancy / completion certificate16 Jun 2021View
Show all 16 documents
Form 416 Jun 2021View
Registration certificate9 Sep 2021View
Form 528 Feb 2022View
OtherView
Layout planView
Building planView
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600017075

Is Shrinathji Palace Co-Opp Housing Society Ltd. delayed?

MahaRERA reports it completed. Its promised completion date was 30 Jun 2023.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600017075.

Who is the promoter?

MahaRERA records Shrinathji Palace CoOpp Hsg Society Ltd as the promoter of P51600017075.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600017075.