Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51600016340

Om Residency · Nashik (M Corp.), Nashik · Tirupati Developers

Promised for 30 Dec 2021 — that date has passed and MahaRERA does not mark the project complete.

4 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600016340

Is Om Residency delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600016340.

Who is the promoter?

MahaRERA records Tirupati Developers as the promoter of P51600016340.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600016340.

Answers are generated from the record.

Data through3 Nov 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology