RegisteredCompletion date passedMahaRERA status: Lapsed

P51600015972

Advait Empire · Nashik (M Corp.), Nashik · Sparsh Buildcon

Promised for 30 Dec 2020 — that date has passed and MahaRERA does not mark the project complete.

5 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Title report21 Mar 2018View
Commencement certificate21 Mar 2018View
Form 121 Mar 2018View
Form 221 Mar 2018View
Form B23 Mar 2018View
Registration certificate18 May 2020View
OtherView
OtherView
Show all 16 documents
Layout planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600015972

Is Advait Empire delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600015972.

Who is the promoter?

MahaRERA records Sparsh Buildcon as the promoter of P51600015972.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600015972.