Completed1 extension

P51600013543

Krissh Infra · Chehedi Bk, Nashik · Krissh Infra

Promised for 30 Sep 2019; MahaRERA reports the project completed.

The revised date is 1 year and 6 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2019 to 29 Mar 2021 (1 extension certificate on record).
  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 17

Title report29 Sep 2017View
Encumbrance details29 Sep 2017View
Commencement certificate29 Sep 2017View
Form B29 Sep 2017View
Form 129 Sep 2017View
Form 229 Sep 2017View
Registration certificate9 Oct 2017View
Extension certificate18 May 2020View
Show all 17 documents
Form 2A18 Jun 2021View
Commencement certificate7 Nov 2023View
Occupancy / completion certificate7 Nov 2023View
OtherView
Layout planView
Building planView
Building planView
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600013543

Is Krissh Infra delayed?

MahaRERA reports it completed. Its promised completion date was 30 Sep 2019.

How many extensions has it had?

Deedo holds 1 extension certificate for P51600013543. The completion date moved from 30 Sep 2019 to 29 Mar 2021.

Who is the promoter?

MahaRERA records Krissh Infra as the promoter of P51600013543.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600013543.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology