RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51600011453

Vijay Samruddhi · Nashik Road, Nashik · V R V Construction

Promised for 3 Dec 2019 — that date has passed and MahaRERA does not mark the project complete.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 3 Dec 2019, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate31 Aug 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P51600011453

Is Vijay Samruddhi delayed?

Yes. MahaRERA records a promised completion of 3 Dec 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600011453.

Who is the promoter?

MahaRERA records V R V Construction as the promoter of P51600011453.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600011453.

Answers are generated from the record.

Data through31 Oct 2026, 01:42SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology