Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Completed

P51600007154

Prabhu Fort · Nashik · Pacific Builders

Promised for 31 Mar 2020; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 31

Title report25 Jul 2017View
Encumbrance details25 Jul 2017View
Commencement certificate25 Jul 2017View
Form B25 Jul 2017View
Form 125 Jul 2017View
Form 228 Jul 2017View
Form 114 Feb 2018View
Form 214 Feb 2018View
Show all 31 documents
Form 122 May 2018View
Form 222 May 2018View
Form 124 Aug 2018View
Form 224 Aug 2018View
Form 529 Sep 2018View
Form 130 Nov 2018View
Form 230 Nov 2018View
Form 120 Mar 2019View
Form 220 Mar 2019View
Form 222 Jun 2019View
Form 424 Jun 2019View
Form 530 Sep 2019View
Form 19 Nov 2019View
Form 29 Nov 2019View
Registration certificate18 May 2020View
Other26 Jul 2021View
OtherView
Layout planView
Building planView
Building planView
Building planView
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600007154

Is Prabhu Fort delayed?

MahaRERA reports it completed. Its promised completion date was 31 Mar 2020.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600007154.

Who is the promoter?

MahaRERA records Pacific Builders as the promoter of P51600007154.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600007154.

Answers are generated from the record.

Data through23 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology