RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51600003147
Malati- Manohar Apt · Nashik (M Corp.), Nashik · Satish Manohar Deshpande
Promised for 30 Dec 2018; MahaRERA reports the project completed.
The revised date is 4 years and 6 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2018 to 30 Jun 2023 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 28
Orders 0
No MahaRERA order or list names this number.
Questions about P51600003147
Is Malati- Manohar Apt delayed?
MahaRERA reports it completed. Its promised completion date was 30 Dec 2018.
How many extensions has it had?
Deedo holds 1 extension certificate for P51600003147. The completion date moved from 30 Dec 2018 to 30 Jun 2023.
Who is the promoter?
MahaRERA records Satish Manohar Deshpande as the promoter of P51600003147.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600003147.
Answers are generated from the record.