Completed

P51600003104

Yogeshwar Residency · Nashik · Yogeshwar Buildcon

Promised for 1 Apr 2020; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Title report31 Jul 2017View
Commencement certificate31 Jul 2017View
Form B31 Jul 2017View
Form 131 Jul 2017View
Form 231 Jul 2017View
Registration certificate18 May 2020View
Occupancy / completion certificate15 Jan 2023View
Form 43 Apr 2023View
Show all 13 documents
OtherView
Layout planView
Allotment letterView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600003104

Is Yogeshwar Residency delayed?

MahaRERA reports it completed. Its promised completion date was 1 Apr 2020.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600003104.

Who is the promoter?

MahaRERA records Yogeshwar Buildcon as the promoter of P51600003104.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600003104.

Answers are generated from the record.