RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51600001553

Laxmi Vandan Apartment · Deolaligaon, Nashik · Rishi Builders And Developers

Promised for 25 Nov 2018, extended once to 25 Nov 2019 — and that date has passed without the project marked complete on MahaRERA.

8 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 25 Nov 2018 to 25 Nov 2019 (1 extension certificate on record).
  • Risk: The latest completion date on record, 25 Nov 2019, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate28 Jul 2017View
Extension certificate19 Mar 2019View

Orders 0

No MahaRERA order or list names this number.

Questions about P51600001553

Is Laxmi Vandan Apartment delayed?

Yes. MahaRERA records a promised completion of 25 Nov 2018, revised to 25 Nov 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51600001553. The completion date moved from 25 Nov 2018 to 25 Nov 2019.

Who is the promoter?

MahaRERA records Rishi Builders And Developers as the promoter of P51600001553.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600001553.

Answers are generated from the record.

Data through1 Nov 2026, 01:39SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology