Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51600000349

Hari Kiran · Vihitgaon, Nashik · Karda Buildcon Private Limited

Promised for 31 Dec 2018 — that date has passed and MahaRERA does not mark the project complete.

7 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate15 Jul 2017View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51600000349

Is Hari Kiran delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51600000349.

Who is the promoter?

MahaRERA records Karda Buildcon Private Limited as the promoter of P51600000349.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51600000349.

Answers are generated from the record.

Data through4 Nov 2026, 03:23SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology