Nabhraj Adwait · Aurangabad (M Corp.), Aurangabad · Nabhraj Construction
Promised for 31 Dec 2027 and not extended so far.
1 year and 2 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51500054571
Is Nabhraj Adwait delayed?
Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51500054571.
Who is the promoter?
MahaRERA records Nabhraj Construction as the promoter of P51500054571.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51500054571.