Nabhraj Construction

Company or firm · 4 projects · 5 MahaRERA registrations · 2 reported completed

4Projects5 RERA registrations
2Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Balaji EnclaveP51500000945Aurangabad (M Corp.)2017Completed3 Oct 201930 Mar 2021+17 months
Nabhraj NandanvanP51500003126Aurangabad (M Corp.)2017Completed31 May 2018—On date
Nabhraj NandanvanP51500021357Aurangabad (M Corp.)2019Certificate Signed29 Jun 202629 Oct 2026+4 months
Nabhraj GharkulP51500051228Aurangabad (M Corp.)2023Certificate Signed31 Dec 202830 Apr 2029+4 months
Nabhraj AdwaitP51500054571Aurangabad (M Corp.)2024Certificate Signed31 Dec 202731 Dec 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Balaji Enclave+17 mo
  • Nabhraj NandanvanOn date
  • Nabhraj Nandanvan+4 mo
  • Nabhraj Gharkul+4 mo
  • Nabhraj AdwaitOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 17 months, for Shree Balaji Enclave (P51500000945).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology