Nabhraj Construction
Company or firm · 4 projects · 5 MahaRERA registrations · 2 reported completed
4Projects5 RERA registrations
2Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shree Balaji EnclaveP51500000945 | Aurangabad (M Corp.) | 2017 | Completed | 3 Oct 2019 | 30 Mar 2021 | +17 months |
| Nabhraj NandanvanP51500003126 | Aurangabad (M Corp.) | 2017 | Completed | 31 May 2018 | — | On date |
| Nabhraj NandanvanP51500021357 | Aurangabad (M Corp.) | 2019 | Certificate Signed | 29 Jun 2026 | 29 Oct 2026 | +4 months |
| Nabhraj GharkulP51500051228 | Aurangabad (M Corp.) | 2023 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Nabhraj AdwaitP51500054571 | Aurangabad (M Corp.) | 2024 | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 17 months, for Shree Balaji Enclave (P51500000945).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology