Completed
P51500050513
Shree Residancy · Aurangabad (M Corp.), Aurangabad · Shree Construction
Promised for 31 Dec 2024; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 44
Orders 0
No MahaRERA order or list names this number.
Questions about P51500050513
Is Shree Residancy delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2024.
How many extensions has it had?
Deedo holds 0 extension certificates for P51500050513.
Who is the promoter?
MahaRERA records Shree Construction as the promoter of P51500050513.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51500050513.
Answers are generated from the record.
Data through23 Nov 2026, 01:46SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology