Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Completed
P51500047705
Sai Suman Pride · Aurangabad (M Corp.), Aurangabad · Aadeshwar Construction
Promised for 24 Nov 2024; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 41
Orders 0
No MahaRERA order or list names this number.
Questions about P51500047705
Is Sai Suman Pride delayed?
MahaRERA reports it completed. Its promised completion date was 24 Nov 2024.
How many extensions has it had?
Deedo holds 0 extension certificates for P51500047705.
Who is the promoter?
MahaRERA records Aadeshwar Construction as the promoter of P51500047705.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51500047705.
Answers are generated from the record.
Data through9 Nov 2026, 02:09SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology