P51500032006

Radhakrishna Nagri · Shendra Kamangar, Aurangabad · Yash Sunil Agrawal And Sattarkha Sardarkha Pathan

Promised for 31 Dec 2023; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 12

Title report3 Nov 2021View
Encumbrance details3 Nov 2021View
Commencement certificate3 Nov 2021View
Form B3 Nov 2021View
Registration certificate3 Dec 2021View
Commencement certificate11 Feb 2023View
Occupancy / completion certificate11 Feb 2023View
OtherView
Show all 12 documents
Layout planView
Commencement certificateView
Building planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500032006

Is Radhakrishna Nagri delayed?

MahaRERA reports it completed. Its promised completion date was 31 Dec 2023.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500032006.

Who is the promoter?

MahaRERA records Yash Sunil Agrawal And Sattarkha Sardarkha Pathan as the promoter of P51500032006.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500032006.