Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

DeregisteredCompletion date passedMahaRERA status: Certificate Signed

P51500031972

Gulmohar Park B · Satara (Ct), Aurangabad · Govind Tikaram Chavan And Teajas Govind Chavan

Promised for 30 Dec 2023 — that date has passed and MahaRERA does not mark the project complete.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2023, has passed.
  • Risk: MahaRERA lists this registration as deregistered.
  • Clear: Completion date never extended.

Documents 1

Registration certificate29 Nov 2021View

Orders 1

Deregistered

Deregistered: GULMOHAR PARK B

matched by RERA number

View order →

Questions about P51500031972

Is Gulmohar Park B delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500031972.

Who is the promoter?

MahaRERA records Govind Tikaram Chavan And Teajas Govind Chavan as the promoter of P51500031972.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51500031972.

Answers are generated from the record.

Data through1 Nov 2026, 02:25SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology