Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51500026531

Construction Of 368 EWS T/S Under PMAY And 168 MIG On S.no.68 At Padhegoan , Dist-Aurangabad · Aurangabad (M Corp.), Aurangabad · Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada)

Promised for 2 Mar 2026 — that date has passed and MahaRERA does not mark the project complete.

8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 2 Mar 2026, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51500026531

Is Construction Of 368 EWS T/S Under PMAY And 168 MIG On S.no.68 At Padhegoan , Dist-Aurangabad delayed?

Yes. MahaRERA records a promised completion of 2 Mar 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500026531.

Who is the promoter?

MahaRERA records Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada) as the promoter of P51500026531.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500026531.

Answers are generated from the record.

Data through23 Nov 2026, 01:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology