RegisteredCompletion date passedMahaRERA status: Lapsed

P51500022845

Arya City - II · Tisgaon, Aurangabad · Rahul Baswant Nandgawali

Promised for 31 Jul 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Jul 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Title report5 Oct 2019View
Encumbrance details5 Oct 2019View
Commencement certificate5 Oct 2019View
Form B18 Oct 2019View
Registration certificate8 Sep 2021View
OtherView
OtherView
Layout planView
Show all 13 documents
Building planView
Allotment letterView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500022845

Is Arya City - II delayed?

Yes. MahaRERA records a promised completion of 31 Jul 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500022845.

Who is the promoter?

MahaRERA records Rahul Baswant Nandgawali as the promoter of P51500022845.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500022845.