Yash Sai Park · Aurangabad (M Corp.), Aurangabad · Yashraj Estates And Developers

Promised for 14 Mar 2023; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Title report25 Sep 2019View
Commencement certificate25 Sep 2019View
Form B25 Sep 2019View
Form 125 Sep 2019View
Form 225 Sep 2019View
Form 225 Dec 2020View
Form 525 Dec 2020View
Registration certificate8 Sep 2021View
Show all 16 documents
Occupancy / completion certificate29 Apr 2023View
Form 45 May 2023View
OtherView
Layout planView
Building planView
Allotment letterView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500022557

Is Yash Sai Park delayed?

MahaRERA reports it completed. Its promised completion date was 14 Mar 2023.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500022557.

Who is the promoter?

MahaRERA records Yashraj Estates And Developers as the promoter of P51500022557.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500022557.