RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51500018970
C R Heights · Aurangabad · C R Builders And Developers
Promised for 1 Dec 2020 — that date has passed and MahaRERA does not mark the project complete.
5 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 1 Dec 2020, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51500018970
Is C R Heights delayed?
Yes. MahaRERA records a promised completion of 1 Dec 2020, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P51500018970.
Who is the promoter?
MahaRERA records C R Builders And Developers as the promoter of P51500018970.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51500018970.
Answers are generated from the record.
