RegisteredCompletion date passedMahaRERA status: Lapsed

P51500016120

Sumitras Beyond · Devlai, Aurangabad · Ravindra Damodhar Baldawa Huf

Promised for 30 Dec 2024 — that date has passed and MahaRERA does not mark the project complete.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 12

Title report9 Apr 2018View
Commencement certificate9 Apr 2018View
Encumbrance details14 Apr 2018View
Form B14 Apr 2018View
Registration certificate9 Sep 2021View
OtherView
OtherView
Layout planView
Show all 12 documents
Building planView
Building planView
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500016120

Is Sumitras Beyond delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500016120.

Who is the promoter?

MahaRERA records Ravindra Damodhar Baldawa Huf as the promoter of P51500016120.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500016120.

Answers are generated from the record.

Data through25 Oct 2026, 01:42SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology