Sumitras Beyond is at latitude 18.63543, longitude 73.81250.
Registered transactions
No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2024
The latest completion date on record passed 1 year and 10 months ago.
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 units registered
Parking
Building
Type
Two-wheeler
Four-wheeler
Bus
Visitor
Total
Building No 1
Closed/Covered
0
0
0
0
6
Building No 1
Open Space
0
0
0
0
0
Building No 2
Closed/Covered
0
0
0
0
7
Building No 2
Open Space
0
0
0
0
0
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Building No 1
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 2
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Common areas and amenities
Internal Roads & FootpathsNot applicable
Internal Roads & FootpathsNot applicable
Internal Roads & FootpathsNot applicable
Internal Roads & FootpathsNot applicable
Internal Roads & FootpathsWORK IN PROGRESS60%
Water SupplyNot applicable
Show all 75 activitiesShow fewer activities
Water SupplyNot applicable
Water SupplyNot applicable
Water SupplyNot applicable
Water Supply1 WELL AND 2 BOREWELL100%
Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
Sewerage (Chamber, Lines, Septic Tank , STP)AMC CHAMBER LINE ATTACHED100%
Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
Storm Water DrainsNot applicable
Storm Water DrainsNot applicable
Storm Water DrainsNot applicable
Storm Water DrainsNot applicable
Storm Water DrainsATTACHED IN WELL100%
Landscaping & Tree PlantingNot applicable
Landscaping & Tree PlantingNot applicable
Landscaping & Tree PlantingNot applicable
Landscaping & Tree PlantingNot applicable
Landscaping & Tree PlantingNot applicable
Street LightingNot applicable
Street LightingNot applicable
Street LightingNot applicable
Street LightingNot applicable
Street LightingNot applicable
Community BuildingsNot applicable
Community BuildingsNot applicable
Community BuildingsNot applicable
Community BuildingsNot applicable
Community BuildingsNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNot applicable
Solid Waste Management And DisposalNot applicable
Solid Waste Management And DisposalNot applicable
Solid Waste Management And DisposalNot applicable
Solid Waste Management And DisposalNot applicable
Solid Waste Management And DisposalNot applicable
Water conservation /Rain water harvestingNot applicable
Water conservation /Rain water harvestingNot applicable
Water conservation /Rain water harvestingNot applicable
Water conservation /Rain water harvestingCOMPLETED100%
Water conservation /Rain water harvestingNot applicable
Energy managemcntNot applicable
Energy managemcntNot applicable
Energy managemcntNot applicable
Energy managemcntNot applicable
Energy managemcntNot applicable
Fire protection and fire safety requirementsNot applicable
Fire protection and fire safety requirementsNot applicable
Fire protection and fire safety requirementsNot applicable
Fire protection and fire safety requirementsNot applicable
Fire protection and fire safety requirementsNot applicable
Electrical meter room, sub-station, receiving stationNot applicable
Electrical meter room, sub-station, receiving stationNot applicable
Electrical meter room, sub-station, receiving stationNot applicable
Electrical meter room, sub-station, receiving stationNot applicable
Electrical meter room, sub-station, receiving stationCOMPLETED100%
Aggregate area of recreational Open SpaceCOMPLETED100%
Aggregate area of recreational Open SpaceNot applicable
Aggregate area of recreational Open SpaceNot applicable
Aggregate area of recreational Open SpaceNot applicable
Aggregate area of recreational Open SpaceNot applicable
Open ParkingNot applicable
Open ParkingNot applicable
Open ParkingNot applicable
Open ParkingNot applicable
Open ParkingCOMPLETED100%
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
12 documents held by Deedo, 16 filings listed on MahaRERA's project page
Proforma allotment letterRAVINDRA BALDAWA -HUF - SALE DEED.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Devlai, Aurangabad taluka
Survey, CTS, gat or plot numbers
7 GUT NO 81 PART C DEVLAI AURANGABADPLOT NO 6PLOT NO 6 TO 12 GUT NO 81 PART B
As published on MahaRERA's project page
PLOT NO 6 TO 12 GUT NO 81 PART B AND PLOT NO 6 AND 7 GUT NO 81 PART C DEVLAI AURANGABAD
Boundaries
North
Plot No 8 And 9 Cidco Layout
South
12 Mtr Wide Road
East
7-5 Mtr Wide Road
West
Gut No 81 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
Role
Name
Registration no.
Architect
Manmeet Singh Arora
—
Source: MahaRERA project page. Contact details are not shown.
Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology