P51500011448

Amar Krishna Kunj · Aurangabad · Amar Builders And Developers

Promised for 30 Dec 2020 — that date has passed and MahaRERA does not mark the project complete.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 May 2020View

Orders 0

No MahaRERA order or list names this number.

Questions about P51500011448

Is Amar Krishna Kunj delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500011448.

Who is the promoter?

MahaRERA records Amar Builders And Developers as the promoter of P51500011448.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500011448.

Answers are generated from the record.

Data through1 Nov 2026, 01:41SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology