RegisteredCompletion date passedMahaRERA status: Lapsed

P51500006362

Town Imperia · Aurangabad (M Corp.), Aurangabad · Town Construction

Promised for 31 Jul 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Jul 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 46

Title report30 Jul 2017View
Encumbrance details31 Jul 2017View
Commencement certificate31 Jul 2017View
Form B31 Jul 2017View
Form 131 Jul 2017View
Form 231 Jul 2017View
Allotment letter31 Jul 2017View
Encumbrance details25 Aug 2017View
Show all 46 documents
Encumbrance details25 Aug 2017View
Encumbrance details25 Aug 2017View
Encumbrance details25 Aug 2017View
Allotment letter21 Nov 2017View
Form 115 Oct 2018View
Form 215 Oct 2018View
Form 515 Oct 2018View
Form 124 Dec 2018View
Form 224 Dec 2018View
Form 224 Dec 2018View
Form 131 Jan 2019View
Form 231 Jan 2019View
Form 531 Oct 2019View
Registration certificate9 Sep 2021View
OtherView
Layout planView
Building planView
Building planView
Building planView
OtherView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500006362

Is Town Imperia delayed?

Yes. MahaRERA records a promised completion of 31 Jul 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500006362.

Who is the promoter?

MahaRERA records Town Construction as the promoter of P51500006362.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500006362.

Answers are generated from the record.

Data through3 Nov 2026, 01:33SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology