Completed

P51500000852

Pride Phoenix · Chikalthana, Aurangabad · Abad Estate Aop

Promised for 30 Dec 2021; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 73

Encumbrance details8 Jul 2017View
Commencement certificate8 Jul 2017View
Form 18 Jul 2017View
Form 28 Jul 2017View
Title report10 Jul 2017View
Form B20 Jul 2017View
Form 12 Dec 2017View
Form 24 Dec 2017View
Show all 73 documents
Form 18 Feb 2018View
Form 28 Feb 2018View
Form 16 Jun 2018View
Form 114 Dec 2018View
Form 114 Dec 2018View
Form 215 Dec 2018View
Form 215 Dec 2018View
Form 215 Dec 2018View
Form 57 Feb 2019View
Form 125 Feb 2019View
Form 225 Feb 2019View
Form 2A5 Mar 2019View
Form 2A27 Apr 2019View
Form 14 Aug 2019View
Form 210 Sep 2019View
Form 121 Sep 2019View
Form 221 Sep 2019View
Form 2A16 Oct 2019View
Form 15 Dec 2019View
Form 25 Dec 2019View
Form 113 Mar 2020View
Form 213 Mar 2020View
Commencement certificate17 Mar 2020View
Form 2A6 Jun 2020View
Form 126 Dec 2020View
Form 226 Dec 2020View
Form 129 Dec 2020View
Form 229 Dec 2020View
Form 119 Jan 2021View
Form 219 Jan 2021View
Occupancy / completion certificate1 Apr 2021View
Occupancy / completion certificate1 Apr 2021View
Occupancy / completion certificate1 Apr 2021View
Occupancy / completion certificate1 Apr 2021View
Occupancy / completion certificate1 Apr 2021View
Occupancy / completion certificate1 Apr 2021View
Occupancy / completion certificate1 Apr 2021View
Form 41 Apr 2021View
Other24 Jul 2021View
Form 2A15 Aug 2021View
Registration certificate9 Sep 2021View
Other19 Feb 2022View
Form 522 Jun 2022View
Form 522 Jun 2022View
Form 52 Jul 2022View
OtherView
Layout planView
Layout planView
Layout planView
Layout planView
Building planView
OtherView
OtherView
Layout planView
Allotment letterView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
Building planView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500000852

Is Pride Phoenix delayed?

MahaRERA reports it completed. Its promised completion date was 30 Dec 2021.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500000852.

Who is the promoter?

MahaRERA records Abad Estate Aop as the promoter of P51500000852.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500000852.

Answers are generated from the record.

Data through23 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology