Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredMahaRERA status: Active

P51100078770

Sai Enclave · Wadi Bk., Nanded · Siddhi Developers

Promised for 31 Mar 2032 and not extended so far.

5 years and 4 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: 2 other MahaRERA orders name this registration.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 26

Form B10 Oct 2024View
Commencement certificate10 Oct 2024View
Commencement certificate10 Oct 2024View
Allotment letter10 Oct 2024View
Other10 Oct 2024View
Other10 Oct 2024View
Title report18 Nov 2024View
Form 118 Nov 2024View
Show all 26 documents
Form 218 Nov 2024View
Encumbrance details17 Dec 2024View
Encumbrance details17 Dec 2024View
Commencement certificate17 Dec 2024View
Other17 Dec 2024View
Other17 Dec 2024View
Other17 Dec 2024View
Other17 Dec 2024View
Other17 Dec 2024View
Other17 Dec 2024View
Other27 Dec 2024View
Registration certificate13 Jan 2025View
OtherView
Layout planView
Allotment letterView
OtherView
OtherView
OtherView

Orders 2

Questions about P51100078770

Is Sai Enclave delayed?

Not so far. MahaRERA records a promised completion of 31 Mar 2032, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51100078770.

Who is the promoter?

MahaRERA records Siddhi Developers as the promoter of P51100078770.

Is it on any MahaRERA regulatory list?

2 MahaRERA orders or lists name P51100078770.

Answers are generated from the record.

Data through23 Nov 2026, 01:54SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology