Registered1 extensionMahaRERA status: Certificate Signed

P51100026409

Manthan Park · Nanded Waghala (M Corp.), Nanded · United Buildcon

Promised for 30 Sep 2022, extended once to 31 Mar 2029, which is still ahead.

The revised date is 6 years and 6 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2022 to 31 Mar 2029 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate8 Sep 2021View
Extension certificate16 Mar 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51100026409

Is Manthan Park delayed?

Its completion moved from 30 Sep 2022 to 31 Mar 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51100026409. The completion date moved from 30 Sep 2022 to 31 Mar 2029.

Who is the promoter?

MahaRERA records United Buildcon as the promoter of P51100026409.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51100026409.

Answers are generated from the record.

Data through30 Oct 2026, 01:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology