P50900027188

Gajanan Plaza 3 · Chandrapur (M Cl), Chandrapur · S V Builders

Promised for 20 Apr 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 20 Apr 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate8 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P50900027188

Is Gajanan Plaza 3 delayed?

Yes. MahaRERA records a promised completion of 20 Apr 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50900027188.

Who is the promoter?

MahaRERA records S V Builders as the promoter of P50900027188.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50900027188.