P50500054902
Unique City 2 · Kanholi, Nagpur · Ganpati Builders And Developers
Promised for 31 Aug 2028, extended to 31 Dec 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Aug 2028 to 31 Dec 2028.
Documents 46
Show all 46 documents
Orders 0
No MahaRERA order or list names this number.
Questions about P50500054902
Is Unique City 2 delayed?
Its completion moved from 31 Aug 2028 to 31 Dec 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500054902. The completion date moved from 31 Aug 2028 to 31 Dec 2028.
Who is the promoter?
MahaRERA records Ganpati Builders And Developers as the promoter of P50500054902.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500054902.