Ganpati Builders And Developers
Of 1 registration whose promised date has arrived, 1 kept it (100%).
Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Uniquevishwa WarangaP50500027078 | Nagpur (Urban) | Certificate Signed | 30 Apr 2025 | 30 Apr 2025 | On date |
| Unique Vishwa-IIP50500047770 | Waranga | Certificate Signed | 26 Oct 2027 | 26 Oct 2027 | On date |
| Unique City 2P50500054902 | Kanholi | Certificate Signed | 31 Aug 2028 | 31 Dec 2028 | +4 mo |