RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
RegisteredMahaRERA status: Certificate Signed
P50500052308
Bhakti Park-3 · Wela Harichandra, Nagpur · Global Logistic Park
Promised for 30 Sep 2027 and not extended so far.
10 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 46
OtherView
Title reportView
Encumbrance detailsView
Encumbrance detailsView
Layout planView
Building planView
Commencement certificateView
Show all 46 documents
Form BView
Form 1View
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
Allotment letterView
OtherView
OtherView
Allotment letterView
OtherView
Form 1View
Form 1View
OtherView
Form 2View
Form 2View
Form 2View
Form 2View
OtherView
Form 1View
Form 2View
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
Form 1View
Form 1View
Form 1View
Orders 0
No MahaRERA order or list names this number.
Questions about P50500052308
Is Bhakti Park-3 delayed?
Not so far. MahaRERA records a promised completion of 30 Sep 2027, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500052308.
Who is the promoter?
MahaRERA records Global Logistic Park as the promoter of P50500052308.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500052308.
Answers are generated from the record.
Data through3 Nov 2026, 02:15SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology