RegisteredCompletion date passedMahaRERA status: Lapsed

P50500050129

P.m.a.y. Scheme Tower A1 42 Ewsdewlling Unit City Survey No 806 Tah Katol Distt Nagpur · Katol (M Cl), Nagpur · P.M.A.Y. Muncipal Council Katol

Promised for 25 Aug 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 25 Aug 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 50

Encumbrance details13 Jan 2023View
Encumbrance details13 Jan 2023View
Commencement certificate13 Jan 2023View
Form B13 Jan 2023View
Allotment letter13 Jan 2023View
Other13 Jan 2023View
Title report25 Jan 2023View
Commencement certificate25 Jan 2023View
Show all 50 documents
Form 125 Jan 2023View
Form 225 Jan 2023View
Other25 Jan 2023View
Other25 Jan 2023View
Other25 Jan 2023View
Encumbrance details25 Jan 2023View
Commencement certificate30 Jan 2023View
Other30 Jan 2023View
Other30 Jan 2023View
Registration certificate20 Mar 2023View
Form 223 Nov 2023View
Form 223 Nov 2023View
Form 223 Nov 2023View
Form 2A23 Nov 2023View
Other23 Nov 2023View
Other23 Nov 2023View
Other23 Nov 2023View
Form 124 Nov 2023View
Form 124 Nov 2023View
Form 124 Nov 2023View
Form 114 Feb 2024View
Form 214 Feb 2024View
Other14 Feb 2024View
Form 128 Apr 2025View
Form 128 Apr 2025View
Form 128 Apr 2025View
Form 128 Apr 2025View
Form 128 Apr 2025View
Form 228 Apr 2025View
Form 228 Apr 2025View
Form 228 Apr 2025View
Form 228 Apr 2025View
Form 228 Apr 2025View
Other28 Apr 2025View
Other28 Apr 2025View
Other28 Apr 2025View
Other28 Apr 2025View
Other28 Apr 2025View
Form 2A28 Apr 2025View
OtherView
Layout planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500050129

Is P.m.a.y. Scheme Tower A1 42 Ewsdewlling Unit City Survey No 806 Tah Katol Distt Nagpur delayed?

Yes. MahaRERA records a promised completion of 25 Aug 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500050129.

Who is the promoter?

MahaRERA records P.M.A.Y. Muncipal Council Katol as the promoter of P50500050129.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500050129.

Answers are generated from the record.

Data through23 Nov 2026, 01:49SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology