RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P50500046629

Gurudeo Nagar -1 · Vihirgaon, Nagpur · Jay Shree Sai Builders & Developers

Promised for 31 Mar 2023, extended once to 30 Mar 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2023 to 30 Mar 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Mar 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 17

Registration certificate25 Aug 2022View
Extension certificate1 Apr 2023View
OtherView
OtherView
Commencement certificateView
Commencement certificateView
Form BView
OtherView
Show all 17 documents
OtherView
Form 1View
Allotment letterView
Form 1View
Form 2View
OtherView
Layout planView
Title reportView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500046629

Is Gurudeo Nagar -1 delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2023, revised to 30 Mar 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P50500046629. The completion date moved from 31 Mar 2023 to 30 Mar 2024.

Who is the promoter?

MahaRERA records Jay Shree Sai Builders & Developers as the promoter of P50500046629.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500046629.