Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500033892

Winter Fall City · Wanadongri, Nagpur · Shivaji Land Builders And Developers

Promised for 1 Jan 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 1 Jan 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 34

Registration certificate14 Mar 2022View
OtherView
OtherView
Form 1View
OtherView
Commencement certificateView
Commencement certificateView
Commencement certificateView
Show all 34 documents
OtherView
Title reportView
Encumbrance detailsView
Layout planView
Form BView
Layout planView
Form 1View
Form 1View
Form 2View
Form 1View
Form 1View
OtherView
OtherView
OtherView
OtherView
Form 1View
Form 1View
Form 1View
Form 1View
Form 1View
Form 2View
Form 2View
Form 2View
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500033892

Is Winter Fall City delayed?

Yes. MahaRERA records a promised completion of 1 Jan 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500033892.

Who is the promoter?

MahaRERA records Shivaji Land Builders And Developers as the promoter of P50500033892.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500033892.

Answers are generated from the record.

Data through3 Nov 2026, 01:57SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology