RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P50500030868
Riaan Corporate Park · Nagpur (M Corp.), Nagpur · Suntech Infraestate Nagpur Private Limited
Promised for 30 Jun 2027, extended to 30 Oct 2027, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2027 to 30 Oct 2027.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 74
Show all 74 documents
Orders 0
No MahaRERA order or list names this number.
Questions about P50500030868
Is Riaan Corporate Park delayed?
Its completion moved from 30 Jun 2027 to 30 Oct 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500030868. The completion date moved from 30 Jun 2027 to 30 Oct 2027.
Who is the promoter?
MahaRERA records Suntech Infraestate Nagpur Private Limited as the promoter of P50500030868.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500030868.
Answers are generated from the record.